CRAC is the consignee receipt and acceptance record used in the relevant GeM process.

Establish a record connecting the accepted order, actual supply, receipt, acceptance, invoice and cash received. Each stage answers a different question. A carrier's delivery attempt can be relevant without proving final conformity, and an uploaded invoice is not necessarily an approved payment. Use the current applicable terms and actual transaction rather than a universal timeline from an old tutorial. Keep partial quantities, disputes and corrections separately visible.
Assign ownership of the next action at each unresolved stage. The delivery team may need to provide evidence, a competent reviewer may need to address a technical question and finance may need to reconcile a remittance. Do not collapse all of these into a generic payment pending label. Banking or profile changes should use proper authority and verification. Preserve official communications and avoid treating an unsolicited caller or commission request as the legitimate route to order acceptance or release of funds.
A fictional seller has a dispatch receipt and an invoice but a quantity discrepancy remains under review. Finance initially expects full payment immediately. The coordinator separates the undisputed accepted portion from the unresolved balance and identifies which evidence the buyer needs next. The example does not decide entitlement or impose a payment deadline. It illustrates why accurate stage information is necessary for follow-up and cash planning, rather than relying on one general completed status.
| Question | Evidence to review |
|---|---|
| Contract commitment | Actual order and authorised amendments |
| Performance | Item, quantity and receipt or acceptance records |
| Billing | Correct invoice and required supporting documents |
| Settlement | Remittance, deductions and bank reconciliation |
Keep exceptions open until an authoritative record or appropriate decision resolves them. This makes later warranty, dispute and closure work easier and avoids representing partial performance, a support ticket or payment initiation as final settlement of the entire contract.
PRC refers to the provisional receipt stage in the relevant GeM goods process. Check the current official terms and actual order to understand what that record establishes and what remains to be inspected or accepted. Physical receipt should not automatically be treated as final conformity or entitlement to the full payment. Match the record to the correct order, items and quantities and retain related delivery evidence. If quantities or condition differ, preserve the discrepancy for resolution. The supplier's operational team and finance team should use the same supported status so goods received are not prematurely reported as finally accepted or a later acceptance issue overlooked.
Confirm the actual delivery and acceptance position before assuming a missing CRAC is merely an administrative delay. Check whether the buyer needs inspection evidence, corrected documents or resolution of a quantity or quality issue. Communicate through the authorised order process, referring to the exact order and supported facts. Preserve delivery records and follow-up without issuing a substitute acceptance certificate yourself. Review the current contractual procedure and escalation route rather than relying on an old universal deadline. Finance should distinguish accepted, pending and disputed amounts so a request for the acceptance record does not conceal an unresolved substantive condition affecting payment.
Identify the stated reason for refusal and preserve the order, dispatch, delivery attempt and product evidence. Distinguish wrong goods, visible damage, missing documents, site unavailability and a disputed requirement; they call for different responses. Use the permitted GeM order and communication process and obtain competent review where technical acceptance is disputed. Do not treat a delivery attempt as completed acceptance or return the goods without considering custody and contract conditions. Record storage, transport and next actions accurately. A factual response should establish what was offered, what arrived and which authorised decision is needed, rather than relying on accusations or informal promises about payment.
Do not replace the contracted model merely because another product is available or appears better. Review the order's substitution provisions and obtain the required technical and commercial approval through an authorised process. Establish specifications, compatibility, certification, warranty and price consequences for the proposed alternative. A catalogue edit or manufacturer's recommendation does not itself amend the buyer's contract. Preserve the original offer and approved change. If the item is discontinued or unavailable, disclose the actual issue promptly with evidence and a realistic proposal. The buyer must receive the goods it has agreed to accept, not an unapproved substitute selected to solve the seller's sourcing problem.
Verify the change through the authorised buyer and official order process before redirecting goods. Compare the new destination with the existing delivery obligation and assess transport, tax documentation, unloading, installation and schedule effects. An informal message from an unfamiliar contact should not establish authority to divert a consignment. Preserve the original instruction, approved change and resulting commercial decision. Update relevant dispatch records only on a supported basis. If the new location changes cost or feasibility, raise that consequence explicitly rather than assuming compensation or absorbing an unreviewed commitment. The delivery team needs one clear current instruction linked to the actual order.
Check whether the actual GeM order permits partial deliveries, the relevant schedule and any conditions affecting inspection, invoicing or completion. Splitting a consignment for convenience does not automatically split the buyer's acceptance or payment obligation. Map each proposed delivery to the ordered items, quantity and location, preserving serial or batch identity where relevant. Obtain any required approval before changing the schedule. Track the outstanding balance separately so an initial receipt is not reported as full completion. If partial delivery is not clearly permitted, seek an authorised resolution rather than assuming a logistics arrangement changes the contracted performance requirement.
Raise a delivery-extension request through the contract's permitted GeM process, explaining the reason, affected quantity, revised programme and supporting evidence. Establish the actual approval authority and timing requirement. A request or buyer conversation is not the same as an approved amendment. Review effects on security, price validity, logistics and any delay-related provisions. Keep the original commitment and authorised revised position together, and notify responsible operational owners. Do not assume silence waives the delivery obligation or penalties. A useful request is specific and realistic, showing how the remaining work can be completed rather than merely asking the buyer to overlook a missed deadline.
Whether a GeM order can be declined, and the consequences of doing so, depend on the actual stage and applicable terms. Review acceptance, cancellation, security and non-performance provisions before acting. An unexpected cost increase is not automatically a right to refuse without consequence. Escalate the facts to the authorised owner and use the permitted platform communication process. Preserve the request and official response rather than relying on a verbal assurance. Distinguish an order that differs from the offer from one the seller simply no longer wishes to perform. Consequential contractual questions require appropriate advice based on the actual documents and commitments already made.
Verify the order in the official GeM system and compare its identity, items, quantities, price, delivery, payment and incorporated conditions with the approved offer. Establish the authorised acceptance action and any prerequisites, such as performance security. Allocate purchasing, logistics, inspection and invoicing responsibilities before committing to suppliers. Identify differences promptly through the permitted channel rather than silently accepting an altered obligation. Preserve the actual order and acceptance record. A procurement win becomes an operational commitment; the team needs to know what must be delivered, where and when, and what evidence the buyer requires before acceptance and payment can progress.
Getting a first GeM order requires more than completing signup. Establish a current, accurate offering, identify suitable buyer requirements and prepare a competitive response the business can genuinely perform. Check relevant category, authorisation and qualification conditions and keep sourcing, cash and support arrangements ready. Do not assume unsolicited calls or payment requests represent genuine buyer interest. Verify actual orders through the official system and review them before acceptance. Measure progress by suitable pursuits and delivery readiness, rather than registration age alone. No legitimate preparation process can guarantee when a buyer will choose the seller, so avoid spending against an order that has not been established.
These official resources are starting points for checking the applicable process. Confirm the current notice, attachments, corrigenda and portal instructions for your own opportunity. A general explanation cannot establish eligibility, an exemption or acceptance for a particular bid. Historical manuals and registration guides may differ from a current screen or contract.
Explore opportunities with BidQuest. Compare a suitable notice with your documented capability before committing money, approving a price or submitting a bid.
Department of Expenditure. Accessed 7 Nov 2026.
Government e Marketplace. Accessed 7 Nov 2026.

Learn how to read government tender documents in India: NIT, eligibility, technical specifications, BOQ, EMD, evaluation, corrigenda and submission checklist.
Read the guide
Learn how Indian MSMEs and contractors can find government tenders on CPPP, GeM and state portals, shortlist relevant notices and track corrigenda.
Read the guide
Prepare a GeM seller registration information checklist covering account ownership, business profile, tax details, authorised signatory and catalogue readiness.
Read the guide